this post was submitted on 13 Nov 2025
932 points (98.2% liked)

Memes

53541 readers
891 users here now

Rules:

  1. Be civil and nice.
  2. Try not to excessively repost, as a rule of thumb, wait at least 2 months to do it if you have to.

founded 6 years ago
MODERATORS
you are viewing a single comment's thread
view the rest of the comments
[–] Horse@lemmygrad.ml 6 points 1 month ago* (last edited 1 month ago)

Each factory would send quantified indices of production processes such as raw material input, production output, number of absentees, etc. These indices would later feed a statistical analysis program that, running on a mainframe computer in Santiago, would make short-term predictions about the factories' performance and suggest necessary adjustments, which, after discussion in an operations room, would be fed back to the factories. This process occurred at 4 levels: firm, branch, sector, and total.

seems pretty centralized to me dawg